Version 1.0 · March 2026
Comprehensive Technical & Project Manual
SEMIUNITIZED
GLAZING
SYSTEMS
Design · Estimation · Survey · Fabrication · Installation · Handover · Warranty · Lab Testing · Site Water Testing
Facade Engineering Glazing Systems Curtain Wall Structural Silicone ASTM / EN
01

Semiunitized (also referred to as Semi-Unitized or Hybrid Stick-Unitized) glazing is a facade system that combines elements of both stick curtain wall and unitized systems. Individual frames or sub-frames are pre-assembled and glazed in the factory, then transported and stacked onto floor-slab anchors or mullion carriers on site, offering faster erection than stick systems while retaining flexibility for tall or complex buildings.

1.1 Key Characteristics

1.2 Typical Panel Configuration

ComponentMaterial / GradeStandard Reference
Extrusion (Frame)AA 6063-T5 / T6 AluminiumIS 733 / ASTM B221
Infill GlassDGU / SGU / PVB LaminatedIS 2553 / EN 1279
Weather SealEPDM / Silicone GasketASTM C864 / ISO 3934
Structural SealantTwo-part SiliconeASTM C1184 / ISO 11600
Panel BracketG.I. / S.S. 304 CleatsIS 2062 / ASTM A240
Thermal BreakPA66 GF25 StripEN 14024
02

2.1 Design Inputs & Criteria

2.2 Structural Design

Semiunitized panels must be engineered for wind pressure (positive & negative), dead load (self-weight) and live loads (maintenance access). Key structural checks include:

2.3 Thermal & Energy Design

U-Value (Tropical)
≤ 2.0
W/m²K
U-Value (Temperate)
≤ 1.6
W/m²K
Thermal Break Min.
20 mm
PA66 GF25 width
SHGC
≤ 0.40
Per energy model

2.4 Acoustic Design

2.5 Drawings & Documentation

03

3.1 Scope of Estimate

3.2 Quantity Takeoff Parameters

ItemUnitBasis of MeasurementWastage Factor
Aluminium ExtrusionkgLinear metre × section wt+8%
Glass (Vision)Panel opening clear area+5%
Glass (Spandrel)Spandrel zone area+5%
Silicone SealantlitreJoint lm × width × depth+10%
EPDM GasketlmPerimeter per panel type+5%
Brackets/AnchorsnosPer panel or per slab+2%
Thermal Break StriplmFrame perimeter length+6%

3.3 Pricing Components

3.4 Estimation Checklist

04

A precise site survey ensures the fabricated panels will fit the as-built structure and that the anchor bracket design accounts for real-world deviations from the architectural grid.

4.2 Survey Instruments

4.3 Survey Parameters

Survey ItemPermissible ToleranceAction if Exceeded
Slab edge plumb (verticality)±15 mm over full heightCustom brackets / shims
Floor-to-floor height variation±10 mmAdjust panel height
Grid line offset (in-out)±10 mmSlotted bracket holes
Slab deflection (pre-facade)Measure and recordInform structural engineer
Column face deviation±8 mmModify anchor detail
Embed plate level±5 mmGrout levelling
Opening width accuracy±6 mmRe-check structural grid

4.4 Survey Process

  1. Establish a primary datum and control grid at each floor level
  2. Survey all slab edges, columns and embed plates floor by floor
  3. Record deviations in a tabulated survey report with AutoCAD overlays
  4. Issue survey report to design team for bracket adjustment
  5. Obtain structural clearance before commencing fabrication
  6. Conduct a final pre-installation check survey before panel delivery

4.5 Survey Documentation

05

5.1 Factory Setup Requirements

5.2 Fabrication Sequence

  1. Receive and verify aluminium extrusion to shop drawing cut list
  2. Cutting to length — double mitre or square cut per frame detail
  3. CNC drilling, routing, notch and hole punching
  4. De-burring and surface cleaning; anodising or powder coating (if applicable)
  5. Thermal break strip insertion and roll-crimping (PA66 GF25)
  6. Frame assembly — corner keys, splice bars, end caps
  7. Weatherstrip / EPDM gasket insertion into extrusion grooves
  8. Structural silicone application for structural glazing (if SSG type)
  9. Glass insertion and mechanical capping or pressure plate fixing
  10. Final QC inspection per panel — visual, dimension, torque check
  11. Panel numbering, wrapping and loading for dispatch

5.3 Quality Control in Fabrication

QC CheckMethod / InstrumentAcceptance Criterion
Panel squarenessDiagonal measurementDiagonal diff ≤ 2 mm
Frame flatnessStraight edge, feeler gauge≤ 2 mm over 2 m
Silicone bite (SSG)Digital calliper at 500 mm c/cMin. 6 mm, no voids
Silicone adhesionPull test on couponsCohesive failure in silicone
Gasket seatingVisual + hand pressureNo gaps or lift-off
Glass positionTape measureEdge clearance ±1 mm
Screw torqueTorque wrenchPer manufacturer spec
Panel dimensionSteel tape±2 mm on W & H

5.4 Mock-up Panel

Prior to full production, a full-size mock-up panel shall be fabricated and subjected to lab testing (Section 8). Only upon satisfactory test results shall production commence. All production panels shall replicate the approved mock-up exactly in terms of materials, section profiles, fixing details and sealant specifications.

06

6.1 Pre-Installation Requirements

6.2 Installation Sequence

  1. Set-out primary installation gridlines at every floor using total station
  2. Install slab brackets / anchor cleats per approved bracket schedule
  3. Fix lower transom carrier or sill track at base of each floor
  4. Hoist and set first panel — align to grid; adjust 3-axis via slotted holes
  5. Install interlock / stack joint cover strip at horizontal joint
  6. Hoist and set subsequent panels on same floor — align horizontally
  7. Fix pressure plates / capping strips; torque to specified value
  8. Apply wet silicone to vertical movement joints between panels
  9. Progress floor by floor; check plumb and level after each floor
  10. Install any fire-stop mineral wool + intumescent at spandrel zone
  11. Install operable vent sashes and hardware
  12. Final alignment check — string line, spirit level, total station
  13. Remove temporary protection film from glass and frame

6.3 Handling & Lifting

6.4 Sealant Application at Joints

6.5 Protection During Construction

07

7.1 Pre-Handover Checklist

7.2 Handover Documentation Package

DocumentSupplied By
As-built shop drawings (PDF + DWG)Facade Contractor
Structural engineering calculations (stamped)Facade Contractor
Lab test reports (mock-up)Accredited Test Lab
Site water test certificates (per floor)Facade Contractor
Material test certificates (aluminium, glass)Manufacturers
Sealant cure certificates & adhesion test recordsSealant Manufacturer
Warranty certificates (all products)Respective Manufacturers
O&M Manual — cleaning, maintenance scheduleFacade Contractor
Spare glass and extrusion supply (min. 1%)Facade Contractor
Safety data sheets (sealants, coatings)Manufacturers

7.3 Maintenance Schedule

Quarterly
Inspect sealant joints
Cracks, loss of adhesion, discolouration
Biannual
Clean facade
pH-neutral detergent and soft cloth/mop
Annual
Inspect hardware
Lubricate and adjust operable hardware
Every 10 Years
Silicone review
Consider joint replacement assessment
Immediate
Replace cracked glass
Do not delay more than 30 days
08

A comprehensive warranty programme for semiunitized glazing covers the performance of individual components as well as the integrated installed facade system. Warranties must be backed by the original manufacturers and the facade contractor respectively.

8.2 Warranty Matrix — By Product

Product / ComponentPeriodCoverage ScopeExclusions
Aluminium Extrusion (Anodised)10 yearsNo chalking, pitting or delamination beyond Grade 15 μmHarsh chemical cleaning; coastal salt spray unless marine grade specified
Aluminium Extrusion (Powder Coat)10 yearsNo peeling, blistering or fading >5 ΔE unitsAbrasion, scratches, graffiti removal
Insulating Glass Unit (DGU)10 yearsNo edge seal failure, condensation between panes, argon loss >5%Breakage due to impact or building movement
Low-E / Solar Control Coating10 yearsNo delamination or loss of optical performance >5%Surface damage from improper cleaning
Structural Silicone Sealant10 yearsNo cohesive/adhesive failure; no deterioration of structural bondMovement exceeding design limits; substrate contamination
Weather / Joint Silicone10 yearsNo cracking, debonding or colour changeImproper joint preparation; design movement exceeded
EPDM Gaskets10 yearsNo permanent set >25%, no crackingUV degradation if exposed beyond design intent
Thermal Break (PA66 GF25)Lifetime of buildingStructural integrity maintainedOverloading beyond design
Facade System (Installed)2 years (workmanship)Watertight performance; no defects in installationActs of God, building settlement, owner modifications

8.3 Warranty Activation Requirements

  1. All materials must be sourced from approved manufacturers and verified by Mill Test Certificates (MTC)
  2. Silicone sealant adhesion tests (7-day and 21-day peel) must pass and be documented
  3. Lab mock-up test report must be submitted and approved before production
  4. Installation must be carried out by trained and certified applicators for structural silicone
  5. Site water test must be completed and passed before handover
  6. O&M manual must be received and acknowledged by building owner/FM team

8.4 Warranty Claim Process

1
NotificationOwner notifies facade contractor in writing within warranty period
2
Joint InspectionSite inspection within 14 days of notification
3
Root Cause AnalysisRCA report issued within 30 days
4
Remediation PlanPlan submitted and agreed within 45 days
5
RectificationWorks completed within agreed timeline — typically 60–90 days
09

All laboratory tests are conducted on full-size mock-up assemblies representing the most critical panel configuration. Tests are performed at an internationally accredited facility (NABL / UKAS / A2LA) before production release.

9.1 Sequence of Tests (ASTM Standards)

#Test NameStandardParametersAcceptance Criteria
1Air InfiltrationASTM E283At 75 Pa (1.57 psf)≤ 0.06 l/s·m² @ 75 Pa
2Static Water PenetrationASTM E331At 137 Pa (2.86 psf); 15 minNo uncontrolled water ingress
3Dynamic Water PenetrationASTM E547Cyclic pressure; 137 PaNo uncontrolled water ingress
4Structural — Design PressureASTM E330+ve and –ve design pressure; 10 min eachDeflection ≤ L/175; no damage
5Structural — Proof LoadASTM E3301.5× design pressure; 10 minNo glass breakage, no permanent set >0.2%
6Inter-storey Drift (Seismic)AAMA 501.4Racking displacement = H/200No glass fallout; operability retained
7Thermal CyclingAAMA 501.5±35°C; 5 cycles eachNo sealant failure, gasket cracking
8Acoustic (Sound Reduction)ISO 140-3 / ASTM E90Rw, Ctr (125 Hz–4000 Hz)Rw ≥ specified (e.g., ≥35 dB)
9Thermal Transmittance (U-value)ISO 10077 / EN 673Whole window U-value calc + hot box test≤ 2.0 W/m²K or as specified
10Solar Heat Gain (SHGC)ISO 9050 / NFRC 200Spectrophotometry of glass build-up≤ 0.40 or per energy model

9.2 Additional Material Tests

TestStandardDetails
Aluminium alloy composition (spectrometry)IS 733 / ASTM B221Verify 6063-T5/T6 grade
Glass thickness & flatnessEN 572 / IS 2835±0.3 mm on thickness
DGU insulating seal integrityEN 1279-2Moisture content < 10 g/m³
Silicone adhesion pull testASTM C794No adhesive failure ≥ 0.14 N/mm²
EPDM compression setASTM D395 Method B≤ 25% at 70°C/22 hours
Thermal break pull-throughEN 14024 Section 6.2≥ 2.0 kN/m capacity
Powder coating adhesionASTM D3359 (Crosscut)Rating ≥ 4B per grid scale
Salt spray (anodising / powder coat)ASTM B1171000 hours; no corrosion creep > 2 mm

9.3 Test Failure Protocol

10

Site water testing verifies the installed facade's watertightness under simulated wind-driven rain conditions. It is performed after panel installation and sealant cure, but before protection film removal and handover. Testing shall be progressive — floor by floor — with results recorded and signed off by the client's representative.

10.2 Test Methods

MethodStandardProcedureApplicable Zones
Hose TestAAMA 501.2Calibrated nozzle; 5 litres/min; 300 mm from surface; 5 min/lm jointLow-rise facades, isolated joints
Static Chamber TestASTM E1105Air pressure box at 137 Pa; spray at 3.4 l/min·m² for 15 minVision panels, mid-rise
Dynamic Chamber TestASTM E1105 (cyclic)Cyclic pressure 0–137 Pa; spray for 15 min totalHigh-rise, hurricane zone
Flood Test (horizontal joints)AAMA 501.2Flood horizontal joint with standing water 25 mm depth for 15 minParapet, horizontal copings

10.3 Testing Parameters & Acceptance Criteria

ParameterValue / ConditionPass Criteria
Test pressure (static)137 Pa (2.86 psf) minimumNo uncontrolled water ingress
Test pressure (dynamic/cyclic)0 to 137 Pa; 5 cyclesNo water beyond inner face of drainage plane
Water application rate3.4 l/min per m² of panelUniform coverage over test area
Duration per test areaMinimum 15 minutes continuousNo ingress during or within 5 min after test
Silicone cure before testMinimum 21 daysSealant fully cured per TDS
Ambient temperature during test5°C – 40°CNo testing in rain, frost or high wind
Wind speed during test< 25 km/hConditions to be recorded in test report
Coverage100% of joints on every floorNo untested joints at handover

10.4 Testing Protocol

  1. Identify all joint types: vertical movement joints, horizontal stack joints, corner joints, window-door perimeters
  2. Seal internal areas with polythene sheeting to detect and trace any ingress precisely
  3. Apply test pressure / hose — start from bottom of facade, work upward
  4. Observer inside building monitors for any water ingress at joints, frame intersections and fastener locations
  5. Any ingress found: stop test, mark location, record on floor sketch
  6. Investigate and rectify — additional silicone, gasket replacement, or bracket adjustment as needed
  7. Re-test rectified areas after minimum 48-hour cure
  8. Issue test certificate per floor — signed by facade contractor QA and client representative

10.5 Common Failure Locations & Remedies

Failure LocationTypical CauseRemedy
Horizontal stack jointInsufficient joint sealant bite or gasket compressionTop up silicone; replace gasket
Vertical movement jointAir pocket in sealant; underfillCut out, clean and re-seal joint
Corner panel junctionComplex geometry; sealant bridgingAdditional silicone fillet; re-tool
Frame/glass perimeterGlazing gasket dislodged in shippingReseat gasket; silicone perimeter if needed
Anchor bracket penetrationNo back-seal at bracket penetrating slab edgeApply fire-rated waterproof sealant around penetration
Transom / mullion butt jointSealant joint too narrow (<6 mm)Saw-cut to minimum 6 mm; reseal

10.6 Test Records to be Maintained

11

11.1 Process Summary

#PhaseKey Output / Deliverable
1DesignStructural calcs, shop drawings, BIM model, energy report
2EstimationBOQ, unit rates, material schedule, risk contingency
3Site SurveyAs-built deviation report, bracket adjustment schedule
4FabricationQC inspection records, mock-up panel, production release
5Lab TestingAccredited test reports (ASTM/EN), product MTCs
6InstallationProgressive installation records, snag list closure
7Water TestingFloor-by-floor test certificates, remediation log
8HandoverFull documentation package, warranties, O&M manual

11.2 Key Standards Referenced

ASTM E283 — Air Infiltration of Windows, Curtain Walls
ASTM E330 — Structural Performance Under Wind Load
ASTM E331 / E547 — Water Penetration (Static / Dynamic)
ASTM E1105 — Field Determination of Water Penetration
AAMA 501.2 — Hose Test Field Check of Metal Curtain Walls
AAMA 501.4 — Static and Dynamic Test Method for Curtain Wall
AAMA 501.5 — Thermal Cycling of Exterior Walls
EN 1279-2 — Insulating Glass Units — Long Term Test
EN 14024 — Thermal Break Test for Aluminium Profiles
ISO 10077 — Thermal Performance of Windows
ISO 140-3 — Acoustic Performance Measurement
IS 875 Part 3 — Wind Loads on Buildings (India)
IS 2553 / IS 2835 — Glass for Glazing
Important Notice This document is a technical guide only. All design, testing and installation must be carried out by qualified professionals in accordance with local building codes, project specifications and relevant international standards. The facade contractor and design engineer of record retain full responsibility for project-specific compliance.